Burlington Alamance Airport Authority
$3.6M+
Prime Contractor, total runway, taxiway and apron rehabilitation. 45 day airport closure (reopened in 41 days to complete runway and apron rehab. 84,000sy of Double Bituminous Surface Treatment followed by 16,750 tons of P401 on the runway.