City of Statesville, NC
$7.8M+
Prime contractor for total runway and taxiway rehabilitation. 14 day airport closure to complete all work on the runway and taxiway F. 25,600 CY of excavation, 49,400 tons of P-209 aggregate base followed by 55,900 tons of P-401 asphalt base and surface course. Project was 60 calendar days to complete above work, and associated electrical, drainage, striping, seeding and other miscellaneous work.